Started: 2008
Completed: 2008

Square Footage: 12,000 SF
Project Cost: $4,800,000

Education Facility
Phase II of Construction

Toward the end of the 2008 summer, this fast-tracked project initiated and 75 days later was completed on time and within budget. The project included six classrooms, offices, bathrooms, a multi-purpose room, and a security niche. With constant and diligent interaction between the SCA, Architect, and Contractor from demolition to final detailing, the end project resulted in complete owner satisfaction and a new positive and safe school environment.