TNS Management
Services Inc
64-55 74th Ave.
Glendale, NY 11385
tel : 718 381 2887
fax :718 381 2339
P.S. 47, P.S. 69, P.S. 96, P.S. 186, P.S. 196
Bronx, NY
General Contractor
Started: 2008
Completed: 2008
Square Footage: 10,000 SF
Project Cost: $4,200,000
Brooklyn, NY
General Contractor
Started: 2008
Completed: 2008
Square Footage: 12,000 SF
Project Cost: $4,800,000
This project was a fast track 75 day job that was completed on time and within budget.
Bronx Science Labs
P.S. 19, P.S. 175, M.S. 327
Bronx, NY
General Contractor
Started: 2008
Completed: 2009
Square Footage: 1,800 SF
Project Cost: $2,400,000
Brooklyn Museum Phase IV
Brooklyn, NY
Prime Contractor
Started: 2008
Completed:
Square Footage: 5,000 SF
Project Cost: $1,800,000
This project is a new out of the ground building that will earn a LEED Certificate
Brooklyn Museum Phase V
Brooklyn, NY
Prime Contractor
Started: 2008
Completed: 2008
Square Footage: 12,000 SF
Project Cost: $1,900,000
P.S. 46 K, P.S. 81 Q, P.S. 147K, P.S. 201Q, P.S. 274K Brooklyn and Queens, NY
General Contractor
Started: 2007
Completed:
Square Footage: 10,000 SF
Project Cost:
JHS 25 Lower East Side Prep
Manhattan, NY
General Contractor
Started: 2007
Completed: 2008
Square Footage: 4,679 SF
Project Cost: $1,957,000
Erasmus High School
Brooklyn, NY
General Contractor
Started: 2007
Completed: 2007
Square Footage: 11,151 SF
Project Cost: $3,450,000
St. Catherines - P.S. 380
Manhattan, NY
Prime Contractor
Started: 2007
Completed: 2007
Square Footage: 15,000 SF
Project Cost: $2,100,000
P.S. 108
Brooklyn, NY
General Contractor
Started: 2007
Completed: 2008
Square Footage: 3,360 SF
Project Cost: $2,056,000
Morris High School - Phase III
Bronx, NY
General Contractor
Started: 2007
Completed: 2007
Square Footage: 2,800 SF
Project Cost: $1,053,000
Brooklyn, NY
Prime Contractor
Started: 2007
Completed: 2008
Square Footage: 120,000 SF
Project Cost: $2,560,000
New Building Construction - Interior and Exterior
P.S. 146 Manhattan
P.S. 196 Brooklyn
P.S. 380 Brooklyn
General Contractor
Square Footage: 6,500 SF
Project Cost: $2,175,000
This program was in partnership with The Robin Hood Foundation and The NYC School Construction Authority.
Morris High School - Phase II
Bronx, NY
General Contractor
Started: 2006
Completed:2006
Square Footage: 9,800 SF
Project Cost: $3,405,000
Far Rockaway H.S.
Queens, NY
General Contractor
Started: 2006
Completed: 2006
Square Footage: 3,000 SF
Project Cost: $1,753,000
Our Lady of Refuge
Brooklyn, NY
General Contract
Started:2006
Completed: 2006
Square Footage: 4,500 SF
Project Cost: $1,532,000
Foot Locker - Kids Queens Center Mall
Queens, NY
General Contractor
Started: 2004
Completed: 2004
Square Footage: 2,160 SF
Project Cost: $348,000
Foot Locker - Champs Queens Center Mall
Queens, NY
General Contractor
Started: 2004
Completed: 2004
Square Footage: 6,600 SF
Project Cost: $511,000
AKA Tenant Fit-Out
Manhattan, NY
General Contractor
Started: 2004
Completed: 2004
Square Footage: 13,000 SF
Project Cost: $650,000
Brooklyn, NY
General Contractor
Square Footage: 4,500 SF
Project Cost: $900,000
Labor and Delivery Room Expansion Project
Brooklyn, NY
General Contractor
Square Footage: 11,250 SF
Project Cost: $2,002,000
This project is a special needs facility for senior adults.